viernes, 24 de abril de 2015

Budget

Budget


























Budget

Progress

The progress since the third week of February until the second week of April. The team focused on the development of the mechanism of his silkscreen automation system distributing the jobs  between each of the members of the team.

We building the structure of the base of prototype, and assemble the motor with the chain, other members designed, elaborated and welded the components in the pcb.

After did the pcb we connect all devices in the board and test the correct operation, the first test there a were few errors and we proceeded to repair.

The we test again the pcb obtaining a positive result. All test were recorded to have evidence.
 When test the motor we saw that the speed was to fast for the prototype because use 12 volts, we decide use 5 volts in the motor to rotate the base and saw that was better.

The prototype have a 85% of progress, we finish in the third week of may.

In conclusion the progress of project was a good result for the work of all  team members.